National Energy Boxing 2X1000MW new project started

Binzhou Daily /Binzhou Net News On the morning of September 27, in Chunchun Town, Boxing County, the National Energy Boxing 2X1000MW new project officially broke ground.

It is understood that the project plans to build two 1000MW thermal power units, using the world's most advanced ultra-supercritical secondary reheating technology, the coal consumption for power generation is only about 80% of the current domestic average level of thermal power units, and simultaneous construction of high-efficiency dust removal and desulfurization , denitrification and other environmental protection facilities, the total investment of the project is about 8.9 billion yuan. After the project is completed and put into operation in 2024, it will have very important practical and strategic significance for the energy security of northern Shandong and even the whole of Shandong.

In order to ensure the smooth start of construction of the National Energy Boxing project, Boxing County convened 16 departments of approval, development and reform, self-regulation, housing construction, water conservancy and other specialized enterprises in municipal newspapers and installations to form a "window acceptance, assistant office". The service model of agency and joint settlement”.

Boxing County Administrative Examination and Approval Service Bureau coordinating with the Drawing Examination Center and other departments to form a full-time team of assistants and agents to make daily scheduling and continuous progress to speed up and improve the project efficiency.

Boxing County also changed the construction permit to be issued in stages according to the overall project, which greatly shortened the construction permit application period and made the project start time 180 days earlier.

In recent years, the Boxing County Party Committee and the County Government have carried out in-depth process reengineering, actively innovating and seeking changes, and exerting multiple efforts to organically integrate, superimpose and upgrade various service methods, continuously stimulate new kinetic energy for service projects, and promote service quality and efficiency and approval. The speed continues to increase, providing strong support for the high-quality economic and social development of the county.