Northeast Network March 10 Daily News (Reporter Fu Wei) At the beginning of the resumption of the Huanggou Power Station of Mudanjiang’s “Top 100 Provincial Projects”, during the special period of epidemic prevention and control, all parties involved in the construction are scientifically dispatching and efficient under the premise of ensuring safety. The construction is expected to complete an investment of 40 million yuan in March.
Huanggou Pumped Storage Power Station construction site.
Huanggou Pumped Storage Power Station is located in Sandaohezi Town, Hailin City. It is one of the top 100 projects in Heilongjiang Province. The No. 1 project in Heilongjiang Province has a total installed capacity of 1.2 million kilowatts and a total investment of 5.803 billion yuan. It will be responsible for Heilongjiang after its completion. Provincial power grid peak shaving, frequency modulation and emergency backup tasks.
According to reports, the current construction unit is mainly engaged in the construction of electromechanical installation projects, divided into 3 construction work surfaces. Among them, the stator working surface of No. 1 unit in the installation room is mainly for stator assembly welding and positioning rib adjustment, laying the foundation for the first unit stator assembly; No. 1 seat ring grinding working surface, installing special grinding tools, and using grinding tools to align the seat ring surface Carrying out finishing; the initial decoration work surface of the installation room floor, and the epoxy artesian floor construction and maintenance work.
In order to ensure safe production during the epidemic, special personnel are arranged to disinfect dormitories and workshops on a regular basis. The temperature of employees is measured twice a day in the morning and evening. All employees are required to wear masks during construction. In order to ensure that the epidemic prevention measures are in place, the company adopts surprise inspections to comprehensively monitor the construction site and living areas. The isolation regulations shall be strictly enforced for the construction personnel returning one after another.
In the next step, the construction unit will, in accordance with the requirements of the provincial and municipal government departments at all levels, take scientific measures in a timely manner to improve construction efficiency, appropriately increase construction personnel and equipment investment, etc., to ensure that the power station is put into operation on schedule.